gantt
    title Our Air Source Heat Pump Install Timeline (2023 to 2025)
    dateFormat YYYY-MM-DD
    axisFormat %b
    todayMarker off
    section Preliminaries
      Onlne quote        :milestone, 2023-10-05, 1d
      Deposit paid       :milestone, 2023-10-09, id
      Q&A call           :milestone, 2023-10-13, 1d
      Pre-install visit  :milestone, 2023-12-19, 1d
      Agreeement signed  :milestone, 2023-12-28, 1d
    section Planning
      Planning permission        :done, 2024-04-11, 2024-06-20
      Planning clarification     :done, 2024-06-27, 2024-09-10
    section Cylinder placement
        1st structural engineer  visit & report         : 2024-04-17, 2024-05-12
        2nd Octopus pre-install visit : milestone, 2024-07-03
        3rd Octopus pre-install visit : milestone, 2024-10-21
        Struvtural engineer re-visit & report         : 2024-10-29, 2024-11-27
    
    section Install readiness
      UK Power Networks Approval :done, 2024-01-02, 2024-01-11
      Drip tray                     :done, milestone, 2024-10-02
      Asbestos survey               :done, 2024-10-24, 2024-10-27
      Boiler Upgrade Scheme voucher :done, 2024-12-18, 2024-12-27
    section Install
      On site install : 2025-01-06, 2025-01-10 