gantt
title Our Air Source Heat Pump Install Timeline (2023 to 2025)
dateFormat YYYY-MM-DD
axisFormat %b
todayMarker off
section Preliminaries
Onlne quote :milestone, 2023-10-05, 1d
Deposit paid :milestone, 2023-10-09, id
Q&A call :milestone, 2023-10-13, 1d
Pre-install visit :milestone, 2023-12-19, 1d
Agreeement signed :milestone, 2023-12-28, 1d
section Planning
Planning permission :done, 2024-04-11, 2024-06-20
Planning clarification :done, 2024-06-27, 2024-09-10
section Cylinder placement
1st structural engineer visit & report : 2024-04-17, 2024-05-12
2nd Octopus pre-install visit : milestone, 2024-07-03
3rd Octopus pre-install visit : milestone, 2024-10-21
Struvtural engineer re-visit & report : 2024-10-29, 2024-11-27
section Install readiness
UK Power Networks Approval :done, 2024-01-02, 2024-01-11
Drip tray :done, milestone, 2024-10-02
Asbestos survey :done, 2024-10-24, 2024-10-27
Boiler Upgrade Scheme voucher :done, 2024-12-18, 2024-12-27
section Install
On site install : 2025-01-06, 2025-01-10
Created
January 12, 2025 17:35
-
-
Save d6y/200b0ea5f5a2994efb3a730bd57b0b23 to your computer and use it in GitHub Desktop.
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment